NEO
500 MW for Meta
- Equipment
- The largest of the seven: 20 small and 7 large gas turbines, 4 gas engines, and a 260-megawatt battery system12
- Settlement
- Signed by every party in the case on October 19, 20267
- Decision
- Could come December 17, The Reporting Project says1
- Air permit
- No draft published yet
More detail: site, schedule, who signed, and the hearing
The plant would sit on about 130 acres in Jersey Township. Construction would start in January 2027, with the plant fully online by December 2028.12
The signers were Will-Power, the City of New Albany, Jersey Township, four Licking County bodies, and the siting board's own staff.7 The evidentiary hearing two days later took 20 minutes, and no one contested the plant.15