We're a group of neighbors in and around New Albany. We want the data centers here, and the gas plants that power them, held to every rule that protects our air, our water and our electric bills, without workarounds.
Last checked against sources on .
Where we stand
We're asking developers, the city and the state for seven things. Open any of them to see the filings and reports behind it.
-
Full Clean Air Act review, taken willingly
Our position: plants this large should accept the full major-source review, including its technology standard and air-quality analysis. They should not file reduced loads, run-hour caps or similar limits whose purpose is to stay under the threshold.
The facts behind it
Under the federal Clean Air Act, a new "major source" of air pollution goes through a review called Prevention of Significant Deterioration. It must install the Best Available Control Technology, show it will not push air quality past federal health standards, and take public input.1 A plant that could emit at major-source levels can avoid that review by accepting enforceable limits that keep its permitted emissions just under the line, which makes it a "synthetic minor" source.2
Ohio EPA plans to treat PowerConneX New Albany 3, a 450 MW plant with 30 gas engines, as a major source for its operating permit. For Prevention of Significant Deterioration, it would count as a minor source.3
-
Best Available Technology on every unit
Our position: developers should apply Best Available Technology to every turbine, engine and backup generator, and not rely on the small-unit exemption.
The facts behind it
-
Don't consume our water
Our position: new data centers should use cooling that doesn't depend on drinking water, such as closed-loop or air cooling, or reclaimed water.
The facts behind it, and the rest of our position
Data centers draw on the same public water system as our homes. Google's New Albany data center alone withdrew about 1 billion gallons in 2025.6
Our position, continued: They should pay the full cost of any water infrastructure they need and publish how much water they use each year.
-
Pay their own way
Our position: data centers and their power plants should cover their full electricity, gas, water and grid costs, without raising residential rates.
The facts behind it, and the rest of our position
According to the independent market monitor for PJM, data center demand has added $29.4 billion to the grid's capacity costs over four auctions.7 Households pay capacity costs through the generation part of their electric bills.8
Our position, continued: Tax breaks should come with public reporting and clawbacks if the promised jobs and investment don't arrive.
-
Build on land that's already been built on
Our position: data centers and their power plants should go on brownfields, former industrial sites and vacant land already zoned for industry, not on working farmland or wetlands.
The facts behind it, and the rest of our position
PowerConneX New Albany 3 alone would take about 59 acres of farmland out of production and permanently affect more than 14 acres of wetlands, according to state siting staff.3
Our position, continued: They should be kept well away from homes and schools.
-
Good union jobs for Ohio workers
Our position: the people who build, run and maintain these facilities should be union workers, paid good wages, and hired and trained in Ohio.
The rest of our position
Our position, continued: Job promises made to win tax breaks should be written down, reported publicly and enforced.
-
Tell neighbors the truth, and listen to them
Our position: residents should know who each project is for, what it will emit and what it will draw, before decisions are made.
The rest of our position
Our position, continued: Emissions monitoring data should be public. Hearings should be held when working families can attend.
What you can do
Add your name below. We'll send you deadlines, hearings and comment guides, so you can tell regulators directly what you expect. See Take part for what is open right now.
Join The Ground Rules
We'll email you before comment deadlines and hearings, with a short guide each time. Only your name, email and ZIP code are required.
Sources
- U.S. EPA, "Prevention of Significant Deterioration Basic Information," accessed Nov. 5, 2026. epa.gov
- 40 CFR 49.167, definition of "synthetic minor source." law.cornell.edu
- OPSB Staff, "Staff Report of Investigation," case 26-0361-EL-BGN (PowerConneX New Albany 3), Oct. 16, 2026, pp. 26–27 (air permit classification); equipment, farmland and wetland figures in the same report. PUCO docket
- U.S. EPA, "Air Plan Approval; Ohio; Ohio Less Than 10 TPY BAT Exemption," 84 Fed. Reg. 14874, Apr. 12, 2019, describing Ohio Adm. Code 3745-31-05 and 2006 Senate Bill 265. govinfo.gov
- See The seven gas plants for each plant's equipment list from its state filings.
- Google, 2026 Environmental Report, p. 97. sustainability.google (PDF)
- Monitoring Analytics (PJM independent market monitor), "Analysis of the 2028/2029 RPM Base Residual Auction, Part A," Oct. 30, 2026. monitoringanalytics.com (PDF)